Roads18PC0039

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES PUDTOL-BAGUTONG ROAD IN SUPPORT OF HANDICRAFT 0+000-1+215, PUDTOL, APAYAO

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES PUDTOL-BAGUTONG ROAD IN SUPPORT OF HANDICRAFT 0+000-1+215, PUDTOL, APAYAO is a DPWH-tracked public work in Apayao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱18,827,403.74. Status: Reported complete (DPWH). Contractor on record: ISNAG BUILDERS. Figures trace to dpwh.

Apayao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction Sabangan Flood Control, Calanasan, Apayao
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVI-18-0003102

₱27,459,000.00 · FY2018

Released to Apayao 2nd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

88 projects · ₱1.9B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - PAVING OF UNPAVED ROADS - TERTIARY ROADS - APAYAO (CALANASAN) - ILOCOS NORTE RD - (S00644LZ) CHAINAGE 6571 - CHAINAGE 8322

Apayao 2nd DEO, Cordillera Administrative Region

2023₱84.5M
Reported complete (DPWH)
No sat.

CSSP- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS(TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-SAN ISIDRO SUR-POBLACION-LAPPA-MARAG-CADACLAN-SALAGUNTING TOURISM ROAD LEADING TO MANACOTA UNDERGROUND RIVER & OTHER TOURISM

Apayao 2nd DEO, Cordillera Administrative Region

2023₱82.0M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF KARAGAWAN RIVER FLOOD CONTROL, STA. 80+321 - STA. 81+162 (R/S), KARAGAWAN,

Apayao 1st DEO, Cordillera Administrative Region

2024₱74.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT-PAVING OF UNPAVED ROADS-TERTIARY ROADS-CLAVERIA-CALANASAN-KABUGAO RD-K0712+000-K0712+144, K0712+228-713+383 - AT SPECIFIC LOCATIONS ALONG CLAVERIA-CALANASAN-KABUGAO RD (S00631LZ)

Apayao 2nd DEO, Cordillera Administrative Region

2022₱67.6M
Reported complete (DPWH)
No sat.

CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION/IMPROVEMENT OF CALABIGAN-CAGANDUNGAN ROAD, BRGY CAGANDUNGAN & BRGY CALABIGAN, LUNA, APAYAO

Apayao 2nd DEO, Cordillera Administrative Region

2025₱66.1M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM PAVING OF UNPAVED ROADS - TERTIARY ROADS CLAVERIA-CALANASAN-KABUGAO ROAD K0710+539 - K0711+061, K0711+126 - K0711+868

Apayao 2nd DEO, Cordillera Administrative Region

2022₱62.0M
Reported complete (DPWH)
View all 88 projects →

4. Implementation

Contract Amount

₱18,827,403.74

Progress

Reported complete (DPWH)

Start Date

February 19, 2018

Target End

August 21, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.