Flood Control and Drainage23DN0031

BASIC INFRASTRUCTURE PROGRAM - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PULONG BANAL (PHASE 2), BARANGAY SAN JOSE, ANTIPOLO CITY, RIZAL (SECOND DISTRICT)

BASIC INFRASTRUCTURE PROGRAM - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PULONG BANAL (PHASE 2), BARANGAY SAN JOSE, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱5,642,947.21. Status: Past target date (DPWH On-Going). Contractor on record: BICOL GOLDROCK CONST CORP. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱6,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Pulong Banal (Phase 2), Barangay San Jose, Antipolo City, Rizal
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Rizal 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

253 projects · ₱14.5B total · 12 flags

Other projects by this contractor

No sat.

CLUSTER I-ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-I-A: REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS-CATANDUANES CIR RD-K0028+000-K0028+647, K0028+788-K0029+000, K

Catanduanes DEO, Region V

2025₱218.7M
Ongoing (DPWH-reported)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BICOL RIVER FLOOD MITIGATION STR

Region V, Region V

2024₱148.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS(TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)PASACAO-BALATAN TOURISM COASTAL HIGHWAY, PASACAO, CAMARINES SUR, PACKAGE 3, CAMARINES SUR(2N

Region V, Region V

2022₱144.8M
Reported complete (DPWH)
No sat.

CSSP: CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - SAN ISIDRO-BAHAO ROAD LEADING TO BAHAO PORT, LIBMANAN, CAMARINES SUR, PACKAGE C

Camarines Sur 2nd DEO, Region V

2025₱143.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD, TAGBAC, RAGAY, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2025₱139.6M
Past target date (DPWH On-Going)

OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG LIBMANAN RIVER (RIGHT SIDE) WITHIN BICOL RIVER BASIN, BARANGAY MA

Camarines Sur 2nd DEO, Region V

2024₱135.1M
Reported complete (DPWH)
View all 253 projects →

4. Implementation

Contract Amount

₱5,642,947.21

Progress

Past target date (DPWH On-Going)

Start Date

February 23, 2023

Target End

August 21, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.