Buildings and Facilities24KK0011

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BERAY, KINOGUITAN, MISAMIS ORIENTAL

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BERAY, KINOGUITAN, MISAMIS ORIENTAL is a DPWH-tracked public work in Misamis Oriental 1st DEO, Region X. Reported contract value: ₱1,980,000.00. Status: Reported complete (DPWH). Contractor on record: CAGALAWAN ENT INC. Figures trace to dpwh.

Misamis Oriental 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure ( Downstream of Cabulawan Bridge ) , Lagonglong, Misamis Oriental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Misamis Oriental 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,980,000.00

Progress

Reported complete (DPWH)

Start Date

February 8, 2024

Target End

May 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.