GAA 2025 OO-125IF0064

CONSTRUCTION OF MISSING LINKS/NEW ROADS, ALBUERA-BURAUEN ROAD(ALBUERA SECTION), PACKAGE 8, ALBUERA, LEYTE

CONSTRUCTION OF MISSING LINKS/NEW ROADS, ALBUERA-BURAUEN ROAD(ALBUERA SECTION), PACKAGE 8, ALBUERA, LEYTE is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱96,165,482.55. Status: Past target date (DPWH On-Going). Contractor on record: BNR CONST. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control/Protection Work of Dam, Tugbong CIS, Kananga, Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Leyte 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

70 projects · ₱4.5B total · 0 flags

Other projects by this contractor

View all 70 projects →

4. Implementation

Contract Amount

₱96,165,482.55

Progress

Past target date (DPWH On-Going)

Start Date

March 27, 2025

Target End

January 20, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.