Roads23IF0077

CONSTRUCTION OF ROAD, ALBUERA, DIVERSION ROAD (PHASE 2), ALBUERA, LEYTE

CONSTRUCTION OF ROAD, ALBUERA, DIVERSION ROAD (PHASE 2), ALBUERA, LEYTE is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱144,749,997.68. Status: Past target date (DPWH On-Going). Contractor on record: BNR CONST. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Boac River, Sitio Naga-Boac, Brgy. Tinag-an, Albuera, Leyte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Leyte 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

70 projects · ₱4.5B total · 0 flags

Other projects by this contractor

View all 70 projects →

4. Implementation

Contract Amount

₱144,749,997.68

Progress

Past target date (DPWH On-Going)

Start Date

June 27, 2023

Target End

May 26, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.