Buildings and Facilities16IE0053

CONSTRUCTION OF CLASSROOMS (1-UNIT, 3-STOREY, 15CL), COMPREHENSIVE HIGH SCHOOLVILLABA, LEYTE

CONSTRUCTION OF CLASSROOMS (1-UNIT, 3-STOREY, 15CL), COMPREHENSIVE HIGH SCHOOLVILLABA, LEYTE is a DPWH-tracked public work in Leyte 3rd DEO, Region VIII. Reported contract value: ₱20,796,155.68. Status: Reported complete (DPWH). Contractor on record: REX E MORALES CONST. Figures trace to dpwh.

Leyte 3rd DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Hindang Flood Control Structures, Hindang, Leyte
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-16-0033091

₱38,917.00 · FY2016

Released to Taganaan National High School (Asa National HigRe (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱20,796,155.68

Progress

Reported complete (DPWH)

Start Date

January 11, 2017

Target End

September 7, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.