Flood Control and Drainage24IH0112

REHABILITATION OF FLOOD CONTROL, CARANGIAN CREEK, BARANGAY SOUTH - BARANGAY WEST, SAN JOSE, NORTHERN SAMAR

REHABILITATION OF FLOOD CONTROL, CARANGIAN CREEK, BARANGAY SOUTH - BARANGAY WEST, SAN JOSE, NORTHERN SAMAR is a DPWH-tracked public work in Northern Samar 1st DEO, Region VIII. Reported contract value: ₱96,468,363.41. Status: Past target date (DPWH On-Going). Contractor on record: RNMK CONST SUPPLY AND DEVELOPMENT CORP FOR: RNMK CONST. Figures trace to dpwh.

Northern Samar 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Bantayan Flood Control Structure, Bantayan River Basin, San Roque, Northern Samar
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Northern Samar 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱96,468,363.41

Progress

Past target date (DPWH On-Going)

Start Date

June 9, 2025

Target End

May 28, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.