Bridges17DF0031

MFO1 NATIONAL ROAD NETWORK SERVICES - CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROAD, WIDENING OF PERMANENT BRIDGES, INCLUDING ROW TO MORE THAN 2 LANES, KANLURAN BRIDGE (B03406LZ); PAG-ASA BRIDGE (B03407LZ) AND GAHAK BRIDGE (B03408LZ) ALONG

MFO1 NATIONAL ROAD NETWORK SERVICES - CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROAD, WIDENING OF PERMANENT BRIDGES, INCLUDING ROW TO MORE THAN 2 LANES, KANLURAN BRIDGE (B03406LZ); PAG-ASA BRIDGE (B03407LZ) AND GAHAK BRIDGE (B03408LZ) ALONG is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱31,359,604.62. Status: Past target date (DPWH On-Going). Contractor on record: CAVDEAL-CAVITE IDEAL INT'L CONST. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Flood Control Structures Along Manila-Cavite Road and Noveleta Diversion Road, Kawit, Cavite
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0009159

₱86,116.00 · FY2017

Released to Division of Camarines Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱31,359,604.62

Progress

Past target date (DPWH On-Going)

Start Date

February 7, 2017

Target End

July 21, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.