Roads18K00238

CLUSTER 37 CONST./UPGRADING/REHAB. OF DRAINAGE ALONG NATIONAL ROADS IN BUKIDNON

CLUSTER 37 CONST./UPGRADING/REHAB. OF DRAINAGE ALONG NATIONAL ROADS IN BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱207,277,779.03. Status: Reported complete (DPWH). Contractor on record: CAVDEAL-CAVITE IDEAL INT'L CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱207,277,779.03

Progress

Reported complete (DPWH)

Start Date

July 17, 2018

Target End

May 19, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.