Water Provision and Storage23F00367

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-WATER SUPPLY SYSTEM-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II, BATO, CAMARINES SUR, NIÑO JESUS, CARICOT, BACOLOD, SALVA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-WATER SUPPLY SYSTEM-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II, BATO, CAMARINES SUR, NIÑO JESUS, CARICOT, BACOLOD, SALVA is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱23,352,938.14. Status: Past target date (DPWH On-Going). Contractor on record: ACIER. Figures trace to dpwh.

Region V, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

24 projects · ₱370.1M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF SEAWALL WITH ROAD DIKE, BARANGAY VIGA, RAPU-RAPU,

Region V, Region V

2025₱141.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF WATER SYSTEM LEVEL II IN BRGY. BALIGANG, BRGY. BONGABON, BRGY. CAGUIBA, BRGY. DEL ROSARIO, BRGY. ILULUAN, AND BRGY. MITI, CAMALIG, ALBAY

Albay 2nd DEO, Region V

2022₱28.4M
Past target date (DPWH On-Going)
No sat.

CLUSTER 14- REPAIR & REHAB. OF CLASSROOMS @ BALADING ELEM. SCHOOL, MALINAO, ALBAY & MALILIPOT NAT'L. HIGH SCHOOL, MALILIPOT, ALBAY

Albay 1st DEO, Region V

2023₱19.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III)-CONSTRUCTION OF VARIOUS SOLAR WATER SYSTEM LEVEL II IN THE MUNICIPALITY OF BALATAN, CAMARINES SUR, PARARAO, SANTIAGO NACACALE, P

Region V, Region V

2023₱19.2M
Past target date (DPWH On-Going)
No sat.

CLUSTER 27-CONSTRUCTION OF WATER SYSTEM LEVEL II, IN THE FIRST DISTRICT OF ALBAY

Albay 1st DEO, Region V

2020₱15.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III)-CONSTRUCTION OF VARIOUS SOLAR WATER SYSTEM LEVEL II IN IRIGA CITY, CAMARINES SUR, SAN NICOLAS, SAN RAMON AND STO. DOMINGO, IRIGA

Region V, Region V

2023₱14.4M
Past target date (DPWH On-Going)
View all 24 projects →

4. Implementation

Contract Amount

₱23,352,938.14

Progress

Past target date (DPWH On-Going)

Start Date

October 31, 2023

Target End

December 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.