Buildings and Facilities23FA0046

CLUSTER 14- REPAIR & REHAB. OF CLASSROOMS @ BALADING ELEM. SCHOOL, MALINAO, ALBAY & MALILIPOT NAT'L. HIGH SCHOOL, MALILIPOT, ALBAY

CLUSTER 14- REPAIR & REHAB. OF CLASSROOMS @ BALADING ELEM. SCHOOL, MALINAO, ALBAY & MALILIPOT NAT'L. HIGH SCHOOL, MALILIPOT, ALBAY is a DPWH-tracked public work in Albay 1st DEO, Region V. Reported contract value: ₱19,552,500.00. Status: Reported complete (DPWH). Contractor on record: ACIER. Figures trace to dpwh.

Albay 1st DEO, Region V
Region: Region V

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2023 · ₱48,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱18,829,056 · ACIER AND BETON CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2022-10-09 → 2025-10-31

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CLUSTER 14- REPAIR & REHAB. OF CLASSROOMS @ BALADING ELEM. SCHOOL, MALINAO, ALBAY & MALILIPOT NAT'L. HIGH SCHOOL, MALILIPOT, ALBAY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱48,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Labnig National High School, Brgy. Labnig, Malinao, Albay
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Albay 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Contract ID No. 23FA0046

₱18,829,055.67 · ACIER AND BETON CONSTRUCTION

Award / contract ref: 23FA0046

Contractor

D

24 projects · ₱370.1M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF SEAWALL WITH ROAD DIKE, BARANGAY VIGA, RAPU-RAPU,

Region V, Region V

2025₱141.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF WATER SYSTEM LEVEL II IN BRGY. BALIGANG, BRGY. BONGABON, BRGY. CAGUIBA, BRGY. DEL ROSARIO, BRGY. ILULUAN, AND BRGY. MITI, CAMALIG, ALBAY

Albay 2nd DEO, Region V

2022₱28.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-WATER SUPPLY SYSTEM-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II, BATO, CAMARINES SUR, NIÑO JESUS, CARICOT, BACOLOD, SALVA

Region V, Region V

2023₱23.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III)-CONSTRUCTION OF VARIOUS SOLAR WATER SYSTEM LEVEL II IN THE MUNICIPALITY OF BALATAN, CAMARINES SUR, PARARAO, SANTIAGO NACACALE, P

Region V, Region V

2023₱19.2M
Past target date (DPWH On-Going)
No sat.

CLUSTER 27-CONSTRUCTION OF WATER SYSTEM LEVEL II, IN THE FIRST DISTRICT OF ALBAY

Albay 1st DEO, Region V

2020₱15.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III)-CONSTRUCTION OF VARIOUS SOLAR WATER SYSTEM LEVEL II IN IRIGA CITY, CAMARINES SUR, SAN NICOLAS, SAN RAMON AND STO. DOMINGO, IRIGA

Region V, Region V

2023₱14.4M
Past target date (DPWH On-Going)
View all 24 projects →

4. Implementation

Contract Amount

₱19,552,500.00

Progress

Reported complete (DPWH)

Start Date

August 11, 2023

Target End

January 7, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)AlbayMalinaoBalading
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.