Water Provision and Storage21HC0145

CONSTRUCTION/ REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, WATER MANAGEMENT FACILITIES, WATER SUPPLY, CONSTRUCTION OF WATERWORKS SYSTEM (LEVEL 3), ZAMORA, TALIBON, BOHOL

CONSTRUCTION/ REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, WATER MANAGEMENT FACILITIES, WATER SUPPLY, CONSTRUCTION OF WATERWORKS SYSTEM (LEVEL 3), ZAMORA, TALIBON, BOHOL is a DPWH-tracked public work in Bohol 2nd DEO, Region VII. Reported contract value: ₱1,008,293.00. Status: Reported complete (DPWH). Contractor on record: PRIMABUILD CONST INC. Figures trace to dpwh.

Bohol 2nd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,978,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Inabanga Flood Control, Inabanga, Bohol
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Bohol 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,008,293.00

Progress

Reported complete (DPWH)

Start Date

May 20, 2021

Target End

July 25, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.