Buildings and Facilities23GD0078

BASIC EDUCATIONAL FACILITIES FUND (BEFF) CONSTRUCTION OF CLASSROOMS BATCH 1 - CONSTRUCTION OF 2STY10CL, CULASI NATIONAL HIGH SCHOOL, ROXAS CITY, CAPIZ

BASIC EDUCATIONAL FACILITIES FUND (BEFF) CONSTRUCTION OF CLASSROOMS BATCH 1 - CONSTRUCTION OF 2STY10CL, CULASI NATIONAL HIGH SCHOOL, ROXAS CITY, CAPIZ is a DPWH-tracked public work in Capiz 1st DEO, Region VI. Reported contract value: ₱24,536,275.60. Status: Reported complete (DPWH). Contractor on record: SALMEGA BUILDERS. Figures trace to dpwh.

Capiz 1st DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

67 projects · ₱836.7M total · 0 flags

4. Implementation

Contract Amount

₱24,536,275.60

Progress

Reported complete (DPWH)

Start Date

September 4, 2023

Target End

August 3, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.