Flood Control and Drainage20JI0053

CONSTRUCTION OF FLOOD CONTROL STRUCTURES (REVETMENT WALL) ALONG IMELDA - BAYOG - KUMALARANG - LAPUYAN - MARGOSATUBIG ROAD PART OF SIBUGUEY RIVER (UPSTREAM), 0000+000 - 0000+052.2

CONSTRUCTION OF FLOOD CONTROL STRUCTURES (REVETMENT WALL) ALONG IMELDA - BAYOG - KUMALARANG - LAPUYAN - MARGOSATUBIG ROAD PART OF SIBUGUEY RIVER (UPSTREAM), 0000+000 - 0000+052.2 is a DPWH-tracked public work in Zamboanga Sibugay 1st DEO, Region IX. Reported contract value: ₱6,051,547.56. Status: Reported complete (DPWH). Contractor on record: MJMARI BUILDERS AND DEVELOPMENT CORP FORMERLY: MJMARI BUILDERS AND ENT. Figures trace to dpwh.

Zamboanga Sibugay 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱6,301,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of flood control structures (revetment wall) along Imelda-Bayog-Kumalarang-Lapuyan-Margosatubig Road part of Sibuguey River (Upstream), Sta. 0+000 - Sta. 0+044, Brgy. Paradise, Diplahan, Zamboanga Sibugay
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Zamboanga Sibugay 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

168 projects · ₱2.2B total · 2 flags

4. Implementation

Contract Amount

₱6,051,547.56

Progress

Reported complete (DPWH)

Start Date

November 24, 2020

Target End

January 25, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.