Roads17P00033

CONSTRUCTION OF BY-PASSES/ DIVERSION ROADS, INCLUDING ROW BAGUIO-LA TRINIDAD-ITOGON-SABLAN-TUBA-TUBLAY (BLISTT) OUTER RING CIRCUMFERENTIAL ROAD, INCL. ROW AND SLOPE PROTECTION, PHASE 2 (LABEY-LACAMEN SECTION, TUBLAY, BENGUET), BENGUET LONE DISTRICT

CONSTRUCTION OF BY-PASSES/ DIVERSION ROADS, INCLUDING ROW BAGUIO-LA TRINIDAD-ITOGON-SABLAN-TUBA-TUBLAY (BLISTT) OUTER RING CIRCUMFERENTIAL ROAD, INCL. ROW AND SLOPE PROTECTION, PHASE 2 (LABEY-LACAMEN SECTION, TUBLAY, BENGUET), BENGUET LONE DISTRICT is a DPWH-tracked public work in Cordillera Administrative Region, Cordillera Administrative Region. Reported contract value: ₱144,749,592.14. Status: Reported complete (DPWH). Contractor on record: ALCEL CONST. Figures trace to dpwh.

Cordillera Administrative Region, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

467 projects · ₱8.0B total · 10 flags

4. Implementation

Contract Amount

₱144,749,592.14

Progress

Reported complete (DPWH)

Start Date

March 16, 2017

Target End

April 24, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.