Rehabilitation / Major Repair of Flood Control Structure23CM0049

Rehabilitation of Flood Control Structure along Sta. Rita River, Olongapo City, Zambales

Rehabilitation of Flood Control Structure along Sta. Rita River, Olongapo City, Zambales is a DPWH-tracked public work in OLONGAPO CITY (ZAMBALES), ZAMBALES, Region III. Reported contract value: ₱77,199,948.01. Status: Reported complete (DPWH). Contractor on record: JAMJLE PROPERTIES SUBIC AND DEVELOPMENT CORPORAT. Figures trace to sumbong.

OLONGAPO CITY (ZAMBALES), ZAMBALES, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱49,580,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Flood Control Structure along Talos Creek (Downstream), Subic, Zambales
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Zambales 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱77,199,948.01

Progress

Reported complete (DPWH)

Start Date

March 15, 2023

Target End

November 25, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.