Flood Control and Drainage25CC0387

CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY CULIANIN TO BARANGAY CAMBAOG, BUSTOS, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY CULIANIN TO BARANGAY CAMBAOG, BUSTOS, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱47,239,394.55. Status: Past target date (DPWH On-Going). Contractor on record: SYMS CONST TRADING. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Barangay Culianin to Barangay Cambaog, Bustos, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱47,239,394.55

Progress

Past target date (DPWH On-Going)

Start Date

March 21, 2025

Target End

November 15, 2025