Roads15FF0086No coordinates published by DPWH

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG GOA-DIGDIGON-SAN ISIDRO ROAD, GOA, CAMARINES SUR K0502+238 - K0503+026.65 W/EXCEPTIONS

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG GOA-DIGDIGON-SAN ISIDRO ROAD, GOA, CAMARINES SUR K0502+238 - K0503+026.65 W/EXCEPTIONS is a DPWH-tracked public work in Camarines Sur 4th DEO, Region V. Reported contract value: ₱20,734,053.01. Status: Reported complete (DPWH). Contractor on record: PARTIDO CONST. Figures trace to dpwh.

Camarines Sur 4th DEO, Region V

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: Region V

No before/after satellite images: DPWH has not published map coordinates for this project, so there is no location to image.

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2016 · ₱5,000 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROV-16-0027986 · ₱243,341 · release to the district office, not itemized per project

    Possible match · score 0.63

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱20,734,053 · PARTIDO CONSTRUCTION & SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Road, cost per km (new paving / upgrading)

₱26,288,897 per km= 1.2x the Region V median (n=151)

Contract cost ₱20,734,053 ÷ 0.789 km read from the DPWH title (“K0502+238 - K0503+026.65”; K-post / station range length). National percentile: 49. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG GOA-DIGDIGON-SAN ISIDRO ROAD, GOA, CAMARINES SUR K0502+238 - K0503+026.65 W/EXCEPTIONS

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Improvement of Quipayo Flood Control, Sto. Niño, Quipayo, Calabanga, Camarines Sur 3rd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-16-0027986

₱243,341.00 · FY2016

Released to Division of Sorsogon (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Road Upgrading (Unpaved to Paved)

₱20,734,053.01 · PARTIDO CONSTRUCTION & SUPPLY

Award / contract ref: 15FF0086

Contractor

B

134 projects · ₱5.3B total · 0 flags

Other projects by this contractor

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY GUINACUTAN, VINZONS, CAMARINES NORTE, VI

Region V, Region V

2024₱198.0M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING PRIMARY ROADS, DAANG MAHARLIKA, K0251+800.00-K0251+887.00; K0251+1048-K0252+700.00; K0252+750.00-K0254+040.00, CAMARINES NORTE

Region V, Region V

2019₱115.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MISSING LINK/NEW ROAD,LALUD - GARCHITORENA ROAD STA.5+713.73 - STA.10+809.63 LAGONOY, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2020₱106.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MISSING LINK/NEW ROAD,(P00402351LZ)LAGONOY-CARAMOAN ROAD SECTION 1: STA.4+390.90 - STA.6+327.41 SECTION 2: STA.7+640.90 - STA.8+204.39 LAGONOY SECTION, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2020₱100.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0277+000-K0278+956, K0278+994-K0279+225, LABO, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT)

Region V, Region V

2025₱100.2M
Past target date (DPWH On-Going)
No sat.

REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS ALONG TIGAON-GOA-SAN JOSE-LAGONOY-GUIJALO VIA SAN VICENTE ROAD K0573+089.00 - K0575+000.00; K0575+233.00 - K0575+522.00; K0575+522.00 - K0575+824.00; K0575+895.00 - K0576+1120.00 CARAMOAN, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2024₱96.5M
Reported complete (DPWH)
View all 134 projects →

4. Implementation

Contract Amount

₱20,734,053.01

Progress

Reported complete (DPWH)

Start Date

February 8, 2016

Target End

April 30, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.