Roads19PC0002

ASSET PRESERVATION REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES (TERTIARY ROADS) ALONG APAYAO(CALANASAN)-ILOCOS NORTE ROAD, K0621+(015)-K0621+085

ASSET PRESERVATION REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES (TERTIARY ROADS) ALONG APAYAO(CALANASAN)-ILOCOS NORTE ROAD, K0621+(015)-K0621+085 is a DPWH-tracked public work in Apayao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱52,071,721.03. Status: Reported complete (DPWH). Contractor on record: REBTRADE INTERNATIONAL CORP. Figures trace to dpwh.

Apayao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXIII-19-0006576

₱44,912,000.00 · FY2019

Released to Apayao 2nd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

61 projects · ₱4.4B total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SIBUYAN CIRCUMFERENTIAL ROAD, KO002+431-KO002+771, ROMBLON

Region IV-B, Region IV-B

2022₱259.0M
Reported complete (DPWH)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGT. PROGRAM, CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF FLOOD MITIGATION STRUCTURES ALONG DUMLOG RIVER (UPSTREAM) BARANGAY CARMEN,

Region VII, Region VII

2023₱193.0M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-NATIONAL ROADS AND BRIDGES-NATIONAL ROADS-PILI-TIGAON-ALBAY BDRY RD.-K0505+700.00-K0505+970.00, SAGNAY,CAMARINES SUR 4TH LEGISLATIVE DISTRICT

Region V, Region V

2021₱193.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AT BALILIHAN, BOHOL

Region VII, Region VII

2024₱192.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SEAWALL, PHASE 1, UBAY, BOHOL

Region VII, Region VII

2025₱188.5M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, MADELLA-DIANADIAWAN ROAD, PROVINCE OF AURORA

Region III, Region III

2022₱188.2M
Reported complete (DPWH)
View all 61 projects →

4. Implementation

Contract Amount

₱52,071,721.03

Progress

Reported complete (DPWH)

Start Date

July 22, 2019

Target End

April 16, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.