Roads22ME0040

BRGY. ALEGRIA PROPER (ALABEL-MALUNGON PRVL. ROAD JUNCTION) TO SITIO LIKON (ALABEL-MALUNGON ROAD), BRGY. DOMOLOK IN SUPPORT TO CACAO, COCONUT, MANGO, AND BANANA AGRI-INDUSTRIES, ALABEL, SARANGANI PROVINCE

BRGY. ALEGRIA PROPER (ALABEL-MALUNGON PRVL. ROAD JUNCTION) TO SITIO LIKON (ALABEL-MALUNGON ROAD), BRGY. DOMOLOK IN SUPPORT TO CACAO, COCONUT, MANGO, AND BANANA AGRI-INDUSTRIES, ALABEL, SARANGANI PROVINCE is a DPWH-tracked public work in Sarangani DEO, Region XII. Reported contract value: ₱9,086,093.14. Status: Reported complete (DPWH). Contractor on record: KGD BUILDERS INC. Figures trace to dpwh.

Sarangani DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bagacay Bridge Flood Control, Alabel, Sarangani
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Sarangani DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,086,093.14

Progress

Reported complete (DPWH)

Start Date

March 13, 2022

Target End

September 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.