Roads17AA0168No coordinates published by DPWH

CONST/UPGRADING/REHAB OF DRAINAGE ALONG LAOAG-AIRPORT RD. KO486+(-622)-KO488+506,KO490+474-KO491+500

CONST/UPGRADING/REHAB OF DRAINAGE ALONG LAOAG-AIRPORT RD. KO486+(-622)-KO488+506,KO490+474-KO491+500 is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱48,860,702.67. Status: Reported complete (DPWH). Contractor on record: KATHA BUILDERS. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I

DPWH did not publish coordinates for this project. Location estimated from the project title (town level only); satellite images may not show the exact site.

Region: Region I

No before/after satellite images: DPWH did not publish coordinates, and the location estimated from the project title is only town level, which is not confident enough to image.

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱45,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-E-17-0017541 · ₱1,955,200 · release to the district office, not itemized per project

    Possible match · score 0.63

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17AA0168 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONST/UPGRADING/REHAB OF DRAINAGE ALONG LAOAG-AIRPORT RD. KO486+(-622)-KO488+506,KO490+474-KO491+500

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bislak River, Brgy. Dagupan, Vintar, Ilocos Norte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0017541

₱1,955,200.00 · FY2017

Released to Regional Office - VI (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

236 projects · ₱11.1B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL J

Cordillera Administrative Region, Cordillera Administrative Region

2022₱289.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLIS

Cordillera Administrative Region, Cordillera Administrative Region

2021₱246.1M
Reported complete (DPWH)
No sat.

BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, GUISSET - BINGA - BALOY - TINONGDAN (SECTION 5 OF BLISTT OUTER RING CIRCUMFERENTIAL ROAD), PACKAGE 1, BENGUETITOGON, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱231.6M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES - CONSTRUCTION OF PIMINGGAN - SAGUITLANG - LUBAS - DUNGON ROAD IN SUPPORT TO COFFEE, CACAO, BAMBOO, GOLD, LIVESTOCK,

Cordillera Administrative Region, Cordillera Administrative Region

2022₱198.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLIS

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION / UPGRADING OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS CITY LIMIT - STO TOMAS ROADKO255+1085

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
View all 236 projects →

4. Implementation

Contract Amount

₱48,860,702.67

Progress

Reported complete (DPWH)

Start Date

May 16, 2017

Target End

January 28, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region I (Ilocos Region)Ilocos NorteCity of Laoag
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.