GAA 2025 OO-125FM0030

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - SN PASCUAL-CLAVERIA RD - K0020+334 - K0020+744, K0022+800 - K0022+858, K0030+000 - K0030+041.

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - SN PASCUAL-CLAVERIA RD - K0020+334 - K0020+744, K0022+800 - K0022+858, K0030+000 - K0030+041. is a DPWH-tracked public work in Masbate 1st DEO, Region V. Reported contract value: ₱33,866,302.50. Status: Past target date (DPWH On-Going). Contractor on record: A3 CONST. Figures trace to dpwh.

Masbate 1st DEO, Region V
Region: Region V

Satellite images pending: this project is in the imagery queue (completed projects first, then ongoing). Before/after images will appear here when it is processed.

Follow the peso

2 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2025 · ₱27,362

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    Not yet linked

  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    44% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Unit-cost benchmark · Road, cost per km (rehabilitation / reconstruction)

₱66,534,975 per km= 1.8x the Region V median (n=146)

Contract cost ₱33,866,303 ÷ 0.509 km read from the DPWH title (“K0020+334 - K0020+744; K0022+800 - K0022+858; K0030+000 - K0030+041”; K-post / station range length). National percentile: 93. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱27,362,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Rizal, Batuan, Masbate
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Masbate 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

47 projects · ₱2.1B total · 0 flags

Other projects by this contractor

No sat.

CSSP- CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM- TRIP)- ESPERANZA- PLACER ROAD LEADING TO PASIAGON BEACH FRONT, BALAY NA BATO AND ESPERANZA SEAPORT, MASBATE (DAAN-LUNGSOD BR.)

Masbate 3rd DEO, Region V

2023₱149.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CSSP- CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM- TRIP)- ESPERANZA- PLACER ROAD LEADING TO PASIAGON BEACH FRONT, BALAY NA BATO AND ESPERANZA SEAPORT, MASBATE

Masbate 3rd DEO, Region V

2023₱144.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-ESPERANZA-PLACER ROAD LEADING TO PASIAGON BEACH FRONT, BALAY NA BATO AND ESPERANZA SEAPORT

Region V, Region V

2022₱143.9M
Reported complete (DPWH)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF DRAINAGE STRUCTURES IN BRGY. BIGAA, BUYUAN, BONGA, PAWA, BOGTONG,

Region V, Region V

2022₱143.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM-ROLL IT) - BALUD NATIONAL ROAD CONNECTING BARANGAY DANA

Masbate 2nd DEO, Region V

2024₱113.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORE PROTECTION STRUCTURE, CLAVERIA, MASBATE.

Masbate 1st DEO, Region V

2025₱93.6M
Past target date (DPWH On-Going)
View all 47 projects →

4. Implementation

Contract Amount

₱33,866,302.50

Progress

Past target date (DPWH On-Going)

Start Date

March 27, 2025

Target End

December 31, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.