Buildings and Facilities22HI0068

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BARANGAY COGON EAST, CARMEN, CEBU

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BARANGAY COGON EAST, CARMEN, CEBU is a DPWH-tracked public work in Cebu 5th DEO, Region VII. Reported contract value: ₱4,948,000.00. Status: Reported complete (DPWH). Contractor on record: RCV VILLAMOR CONST. Figures trace to dpwh.

Cebu 5th DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Lahug River, Cebu City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Cebu 5th DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

63 projects · ₱558.9M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, CARMEN, CEBU

Cebu 5th DEO, Region VII

2024₱49.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS CEBU NORTH HAGNAYA WHARF RD - K0039+000 - K0041+500

Cebu 5th DEO, Region VII

2024₱48.2M
Past target date (DPWH On-Going)
No sat.

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF SITIO SANTICAN TO BARANGAY LANIPGA ROAD, MUNICIPALITY OF CARMEN, CEBU

Cebu 5th DEO, Region VII

2025₱48.0M
Past target date (DPWH On-Going)
No sat.

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD LEADING TO TOURIST DESTINATION AT ALBOR CAVE, CARMEN, CE

Cebu 5th DEO, Region VII

2025₱48.0M
Past target date (DPWH On-Going)
No sat.

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BLDGS/ FACILITIES - CONSTRUCTION OF ROAD, BRGY. COGON - BRGY. LOWER NATIMA-AN - BRGY. LANIPGA, CARMEN

Cebu 5th DEO, Region VII

2025₱38.4M
Past target date (DPWH On-Going)
No sat.

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CAURASAN ROAD LEADING TO TOURIST DESTINATION AT MT. KAPAY

Cebu 5th DEO, Region VII

2025₱28.8M
Past target date (DPWH On-Going)
View all 63 projects →

4. Implementation

Contract Amount

₱4,948,000.00

Progress

Reported complete (DPWH)

Start Date

May 31, 2022

Target End

September 27, 2022

5. Audit