Construction of Flood Mitigation Structure22IC0075

Construction of Flood Control Structure Along Dungon River, Brgy. Rizal II, Babatngon, Leyte

Construction of Flood Control Structure Along Dungon River, Brgy. Rizal II, Babatngon, Leyte is a DPWH-tracked public work in BABATNGON (LEYTE), LEYTE, Region VIII. Reported contract value: ₱29,679,661.26. Status: Reported complete (DPWH). Contractor on record: GO_SOLID BUILDERS INC. Figures trace to sumbong.

BABATNGON (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Along Dungon River, Brgy. Rizal II, Babatngon, Leyte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003175

₱520,522,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003115

₱30,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003139

₱25,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱29,679,661.26

Progress

Reported complete (DPWH)

Start Date

May 20, 2022

Target End

December 26, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.