Roads19EH0009

PAVING OF UNPAVED ROADS ALONG SIBUYAN CIRCUMFERENTIAL ROAD, K0050 + 624.20 - K0051 + 317, K0072 + 675 - K0074 + 001.90 (AS PER ACTUAL)K0050 + 635.20 - K0051 + 317, K0072 + 675 - K0073 + 990.90 (AS PER RBIA), SIBUYAN ISLAND, ROMBLON

PAVING OF UNPAVED ROADS ALONG SIBUYAN CIRCUMFERENTIAL ROAD, K0050 + 624.20 - K0051 + 317, K0072 + 675 - K0074 + 001.90 (AS PER ACTUAL)K0050 + 635.20 - K0051 + 317, K0072 + 675 - K0073 + 990.90 (AS PER RBIA), SIBUYAN ISLAND, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱38,651,438.41. Status: Reported complete (DPWH). Contractor on record: MT GUITING-GUITING CONST. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-19-0004305

₱545,008.00 · FY2019

Released to Rajah Soliman Science and Technology High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱38,651,438.41

Progress

Reported complete (DPWH)

Start Date

July 8, 2019

Target End

January 8, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.