Roads23K00134

ROAD WIDENING-SECONDARY ROADS, WAO-BUMBARAN SECTION - (S01605MN) CHAINAGE 6000 - CHAINAGE 8000

ROAD WIDENING-SECONDARY ROADS, WAO-BUMBARAN SECTION - (S01605MN) CHAINAGE 6000 - CHAINAGE 8000 is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱45,705,472.63. Status: Reported complete (DPWH). Contractor on record: M M A ACHIEVER CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱45,705,472.63

Progress

Reported complete (DPWH)

Start Date

September 8, 2023

Target End

May 4, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.