Roads24HC0064

CONCRETING OF BRGY. SAN MIGUEL TO BRGY. BABAG FMR, BRGY. SAN MIGUEL AND BRGY. BABAG, DAGOHOY, BOHOL

CONCRETING OF BRGY. SAN MIGUEL TO BRGY. BABAG FMR, BRGY. SAN MIGUEL AND BRGY. BABAG, DAGOHOY, BOHOL is a DPWH-tracked public work in Bohol 2nd DEO, Region VII. Reported contract value: ₱14,914,310.76. Status: Reported complete (DPWH). Contractor on record: D' 5J CONST. Figures trace to dpwh.

Bohol 2nd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of San Francisco Bridge Flood Control Structure, Ubay, Bohol
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bohol 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,914,310.76

Progress

Reported complete (DPWH)

Start Date

May 14, 2024

Target End

August 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.