Buildings and Facilities18JC0077

CONSTRUCTION OF TWO (2) UNITS THREE (3) STOREY SIX (6) CLASSROOM REGULAR WORKSHOP W/ TOILET BUILDING AT LILOY NATIONAL HIGH SCHOOL, LILOY, ZAMBOANGA DEL NORTE

CONSTRUCTION OF TWO (2) UNITS THREE (3) STOREY SIX (6) CLASSROOM REGULAR WORKSHOP W/ TOILET BUILDING AT LILOY NATIONAL HIGH SCHOOL, LILOY, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Zamboanga del Norte 3rd DEO, Region IX. Reported contract value: ₱56,289,568.22. Status: Reported complete (DPWH). Contractor on record: LONG ISLAND BUILDERS. Figures trace to dpwh.

Zamboanga del Norte 3rd DEO, Region IX
Region: Region IX

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱30,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROIX-18-0014811 · ₱372,892 · release to the district office, not itemized per project

    Possible match · score 0.81

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18JC0077 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-01-30 → 2025-04-14

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF TWO (2) UNITS THREE (3) STOREY SIX (6) CLASSROOM REGULAR WORKSHOP W/ TOILET BUILDING AT LILOY NATIONAL HIGH SCHOOL, LILOY, ZAMBOANGA DEL NORTE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, De Venta Perla (Sergio Osmeña side), Including RROW, Zamboanga del Norte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIX-18-0014811

₱372,892.00 · FY2018

Released to (Zamboanga Regional Science High 2018 School) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

275 projects · ₱5.6B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PULIRAN RIVER, PULIRAN BR. SECTION PACKAGE 2, SIBUCO, ZAMBOANGA DEL NORTE

Region IX, Region IX

2024₱164.0M
Past target date (DPWH On-Going)
No sat.

ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY BALAKAN-BARANGAY CALUCAP ROAD, SALUG, ZAMBOANGA DEL NORTE

Region IX, Region IX

2025₱153.0M
Past target date (DPWH On-Going)

CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIOCON RIVER (DOWNSTREAM), SIOCON, ZAMBOANGA DEL NORTE, PACKAGE 2

Region IX, Region IX

2024₱137.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SALUG RIVER AT SALUG BR. SECTION (B00528MN) ALONG SINDANGAN-LILOY ROAD (S01142MN), SALUG, ZAMBOANGA DEL NORTE, PACKAGE 1

Region IX, Region IX

2024₱128.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH ESPLANADE AT SALUG BRIDGE (B00528MN), SALUG, ZAMBOANGA DEL NORTE

Region IX, Region IX

2023₱109.9M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KIPIT RIVER, GUTALAC, ZAMBOANGA DEL NORTE (UPSTREAM) STA. 0 + 204 - 0 + 604

Zamboanga del Norte 3rd DEO, Region IX

2024₱95.5M
Reported complete (100% progress, DPWH status On-Going)
View all 275 projects →

4. Implementation

Contract Amount

₱56,289,568.22

Progress

Reported complete (DPWH)

Start Date

July 8, 2018

Target End

February 27, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.