Flood Control and Drainage25AA0142

FLOOD MANAGEMENT PROGRAM - CONS/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAOAG RIVER BASIN AND TRIBUTARIES, DAURAO CREEK, BARANGAY CASILI, LAOAG CITY, I.N.

FLOOD MANAGEMENT PROGRAM - CONS/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAOAG RIVER BASIN AND TRIBUTARIES, DAURAO CREEK, BARANGAY CASILI, LAOAG CITY, I.N. is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱47,044,202.02. Status: Past target date (DPWH On-Going). Contractor on record: IGWT-JAV CONST. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Laoag River Basin and Tributaries, Daurao Creek, Barangay Casili, Laoag City, Ilocos Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Ilocos Norte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

39 projects · ₱1.9B total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG NAYOM RIVER, SEGMENT B, BARANGAY POTOL, INFANTA, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱94.6M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG NAYOM RIVER, SEGMENT A, BARANGAY POTOL, INFANTA, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱94.6M
Past target date (DPWH On-Going)
No sat.

CONS./MAINTENANCE OF FLOOD MITIGATIONSTRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OFFLOOD MITIGATING STRUCTURE ALONG PADSAN RIVERCONNECTING BARANGAY 6 TONOTON, PIDDIG, ILOCOS NORTEAND BARANGAY SAN MARCOS, SITIO CABULOAN, SARRAT, ILOCOSNORTE

Ilocos Norte 1st DEO, Region I

2024₱77.2M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BANK SLOPE ALONG BAYAMBANG RIVER, STA. 001+523.2 - STA. 002+033.2, BARANGAY BAYAMBANG, INFANTA, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱70.9M
Past target date (DPWH On-Going)
No sat.

SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR LED STREET LIGHTS ALONG ALAMINOS-BOLINAO ROAD K0357+660-K0361+140, BOLINAO, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱70.9M
Past target date (DPWH On-Going)
No sat.

SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR LED STREET LIGHTS ALONG ALAMINOS-BOLINAO ROAD, K0354+180-K0357+660, BOLINAO, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱70.9M
Past target date (DPWH On-Going)
View all 39 projects →

4. Implementation

Contract Amount

₱47,044,202.02

Progress

Past target date (DPWH On-Going)

Start Date

February 13, 2025

Target End

August 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.