Flood Control and Drainage24AA0106

CONS./MAINTENANCE OF FLOOD MITIGATIONSTRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OFFLOOD MITIGATING STRUCTURE ALONG PADSAN RIVERCONNECTING BARANGAY 6 TONOTON, PIDDIG, ILOCOS NORTEAND BARANGAY SAN MARCOS, SITIO CABULOAN, SARRAT, ILOCOSNORTE

CONS./MAINTENANCE OF FLOOD MITIGATIONSTRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OFFLOOD MITIGATING STRUCTURE ALONG PADSAN RIVERCONNECTING BARANGAY 6 TONOTON, PIDDIG, ILOCOS NORTEAND BARANGAY SAN MARCOS, SITIO CABULOAN, SARRAT, ILOCOSNORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱77,199,499.85. Status: Past target date (DPWH On-Going). Contractor on record: IGWT-JAV CONST. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigating Structure along Padsan River connecting Barangay 6 Tonoton, Piddig, Ilocos Norte and Barangay San Marcos, Sitio Cabuloan, Sarrat, Ilocos Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-24-0001863

₱13,715,152.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

39 projects · ₱1.9B total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG NAYOM RIVER, SEGMENT A, BARANGAY POTOL, INFANTA, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱94.6M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG NAYOM RIVER, SEGMENT B, BARANGAY POTOL, INFANTA, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱94.6M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BANK SLOPE ALONG BAYAMBANG RIVER, STA. 001+523.2 - STA. 002+033.2, BARANGAY BAYAMBANG, INFANTA, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱70.9M
Past target date (DPWH On-Going)
No sat.

SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR LED STREET LIGHTS ALONG ALAMINOS-BOLINAO ROAD K0357+660-K0361+140, BOLINAO, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱70.9M
Past target date (DPWH On-Going)
No sat.

SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR LED STREET LIGHTS ALONG ALAMINOS-BOLINAO ROAD, K0354+180-K0357+660, BOLINAO, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱70.9M
Past target date (DPWH On-Going)
No sat.

SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR LED STREET LIGHTS ALONG PANGASINAN-ZAMBALES ROAD, K0279+980-K0283+460, DASOL, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱70.9M
Past target date (DPWH On-Going)
View all 39 projects →

4. Implementation

Contract Amount

₱77,199,499.85

Progress

Past target date (DPWH On-Going)

Start Date

March 1, 2024

Target End

February 2, 2025

5. Audit