Roads22C00064

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BYPASS AND DIVERSION ROADS, CONCEPCION-MABALACAT BYPASS ROAD, PROVINCE OF TARLAC

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BYPASS AND DIVERSION ROADS, CONCEPCION-MABALACAT BYPASS ROAD, PROVINCE OF TARLAC is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱105,595,125.00. Status: Reported complete (DPWH). Contractor on record: C. Figures trace to dpwh.

Region III, Region III
Region: Region III

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱102,345,674 · C & F CONSTRUCTION AND DEVELOPMENT

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2021-10-29 → 2025-11-18

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BYPASS AND DIVERSION ROADS, CONCEPCION-MABALACAT BYPASS ROAD, PROVINCE OF TARLAC

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

22C00064

₱102,345,673.83 · C & F CONSTRUCTION AND DEVELOPMENT

Award / contract ref: 22C00064

Contractor

B

231 projects · ₱6.0B total · 0 flags

4. Implementation

Contract Amount

₱105,595,125.00

Progress

Reported complete (DPWH)

Start Date

June 27, 2022

Target End

May 11, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.