Construction of Flood Mitigation Structure24HJ0103

Construction of Flood Control Structure along Hibaiyo River Upstream, Guihulngan City, Negros Oriental

Construction of Flood Control Structure along Hibaiyo River Upstream, Guihulngan City, Negros Oriental is a DPWH-tracked public work in CITY OF GUIHULNGAN (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII. Reported contract value: ₱57,900,000.00. Status: Reported complete (DPWH). Contractor on record: HOMEWORLD CONST CORP FORMERLY HOMEWORLD E. Figures trace to sumbong.

CITY OF GUIHULNGAN (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Calamba River, Guihulngan City, Negros Oriental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0007805

₱1,487,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0002591

₱233,883.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0007808

₱137,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

138 projects · ₱5.2B total · 3 flags

4. Implementation

Contract Amount

₱57,900,000.00

Progress

Reported complete (DPWH)

Start Date

March 7, 2024

Target End

November 20, 2024