Buildings and Facilities16FD0040

CLUSTER PROJECTS: CONST. OF CLASSROOMS (BATCH 9) AT A) CARANAN ES (NORTH), PASACAO, CS B) SALVACION ES, PASACAO CS C) SAN ANTONIO ES PASACAO, CS AND D)ANTIPOLO HEIGHTS INTEGRATED SCHOOL, PASACAO, CS

CLUSTER PROJECTS: CONST. OF CLASSROOMS (BATCH 9) AT A) CARANAN ES (NORTH), PASACAO, CS B) SALVACION ES, PASACAO CS C) SAN ANTONIO ES PASACAO, CS AND D)ANTIPOLO HEIGHTS INTEGRATED SCHOOL, PASACAO, CS is a DPWH-tracked public work in Camarines Sur 2nd DEO, Region V. Reported contract value: ₱8,552,424.64. Status: Reported complete (DPWH). Contractor on record: E P L GEN CONST AND SUPPLY INC. Figures trace to dpwh.

Camarines Sur 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation and Improvement of Calabanga Flood Control (Waterways), Brgy. Sabang - Salvacion Baybay - San Roque - San Pablo, Calabanga, Camarines Sur 3rd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0014680

₱1,739,720.00 · FY2016

Released to Allen National High School (Balicuatro NHS) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

62 projects · ₱974.8M total · 0 flags

4. Implementation

Contract Amount

₱8,552,424.64

Progress

Reported complete (DPWH)

Start Date

August 25, 2016

Target End

November 17, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.