Buildings and Facilities19HC0125

CONSTRUCTION/IMPROVEMENT OF MULTIPURPOSE BUILDING, AGUINING, PRES. C.P. GARCIA, BOHOL

CONSTRUCTION/IMPROVEMENT OF MULTIPURPOSE BUILDING, AGUINING, PRES. C.P. GARCIA, BOHOL is a DPWH-tracked public work in Bohol 2nd DEO, Region VII. Reported contract value: ₱970,000.00. Status: Reported complete (DPWH). Contractor on record: MAI CONST. Figures trace to dpwh.

Bohol 2nd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-19-0011352

₱9,308,000.00 · FY2019

Released to Sikatuna National Agricultural High Sch (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

169 projects · ₱806.4M total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-TERTIARY ROADS - GUIHULNGAN - BALOC - ISABELA RD - K0117 + 825 - K0118 + 308, K0119 + 000- K0119 + 096, K0119 + 418 - K0119 + 650, K0126 + 029 - K01

Negros Oriental 1st DEO, Negros Island Region

2022₱26.5M
Reported complete (DPWH)
No sat.

BASIC EDUCATIONAL FACILITIES FUND (BEFF)- BATCH 1: CONSTRUCTION OF 2STY8CL SCHOOL BUILDING, DAGOHOY NATIONAL HIGH SCHOOL, DAGOHOY, BOHOL

Bohol 2nd DEO, Region VII

2023₱24.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), CARLOS P. GARCIA, BOHOL (PHASE 3)

Bohol 2nd DEO, Region VII

2024₱19.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF JCT. DUMAGUETE NORTH ROAD

Negros Oriental 1st DEO, Negros Island Region

2025₱14.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON ROAD GRAVEL STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) MABINAY - AYUNGON ROAD, AYUNGON, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2018₱12.9M
Reported complete (DPWH)
No sat.

REHABILITATION (COMPLETION) OF DPWH BOHOL 2ND DEO INCLUDING OTHER FACILITIES, UBAY, BOHOL

Bohol 2nd DEO, Region VII

2023₱12.7M
Reported complete (DPWH)
View all 169 projects →

4. Implementation

Contract Amount

₱970,000.00

Progress

Reported complete (DPWH)

Start Date

July 18, 2019

Target End

September 30, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.