Bridges20PB0003

NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS, ABRA-KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL-PINUKPUK), PACKAGE 1, APAYAO - CONSTRUCTION OF CONCRETE BRIDGE

NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS, ABRA-KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL-PINUKPUK), PACKAGE 1, APAYAO - CONSTRUCTION OF CONCRETE BRIDGE is a DPWH-tracked public work in Apayao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: ENRIQUE T CHUA CONST DEVELOPMENT CORP. Figures trace to dpwh.

Apayao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Nabuangan (upstream) Flood Control, Brgy. Cupis, Conner, Apayao
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Apayao 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

10 projects · ₱387.7M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/ NEW ROADS, ABRA-KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL-PINUKPUK), PACKAGE 1, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2024₱117.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONBAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS, APAYAO-KALINGA-ABRA RD.(BULUAN-SACPIL-WAGUD-TAWANG-SALEGSEG SECT.) - (S00695LZ)-CHAINAGE 0- CHAINAGE 3900

Apayao 1st DEO, Cordillera Administrative Region

2025₱60.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS, APAYAO-KALINGA-ABRA RD (BULUAN-SACPIL-WAGUD-TAWANG-SALEGSEG SECT.) - (S00695LZ) - CHAINAGE 8158 - CHAINAGE

Apayao 1st DEO, Cordillera Administrative Region

2025₱52.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (APAYAO TOURISM BUILDING), LUNA, APAYAO

Apayao 2nd DEO, Cordillera Administrative Region

2023₱29.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/ NEW ROADS, ABRA- KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL-PINUKPUK), PACKAGE 2, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2024₱28.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/ NEW ROADS, ABRA-KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL-PINUKPUK),PACKAGE 2, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2022₱19.6M
Reported complete (DPWH)
View all 10 projects →

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

November 5, 2020

Target End

December 29, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.