GAA 2025 OO-125PB0002

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS, APAYAO-KALINGA-ABRA RD (BULUAN-SACPIL-WAGUD-TAWANG-SALEGSEG SECT.) - (S00695LZ) - CHAINAGE 8158 - CHAINAGE

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS, APAYAO-KALINGA-ABRA RD (BULUAN-SACPIL-WAGUD-TAWANG-SALEGSEG SECT.) - (S00695LZ) - CHAINAGE 8158 - CHAINAGE is a DPWH-tracked public work in Apayao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱52,012,766.39. Status: Past target date (DPWH On-Going). Contractor on record: ENRIQUE T CHUA CONST DEVELOPMENT CORP. Figures trace to dpwh.

Apayao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱85,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Matalag (Downstream) Flood Mitigation Structures, STA. 33+288 - STA. 34+248, with exceptions, Conner, Apayao
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Apayao 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction Projects

₱52,012,766.39 · ENRIQUE T. CHUA CONSTRUCTION DEVELOPMENT

Contractor

10 projects · ₱387.7M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/ NEW ROADS, ABRA-KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL-PINUKPUK), PACKAGE 1, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2024₱117.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONBAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS, APAYAO-KALINGA-ABRA RD.(BULUAN-SACPIL-WAGUD-TAWANG-SALEGSEG SECT.) - (S00695LZ)-CHAINAGE 0- CHAINAGE 3900

Apayao 1st DEO, Cordillera Administrative Region

2025₱60.4M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS, ABRA-KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL-PINUKPUK), PACKAGE 1, APAYAO - CONSTRUCTION OF CONCRETE BRIDGE

Apayao 1st DEO, Cordillera Administrative Region

2020₱49.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (APAYAO TOURISM BUILDING), LUNA, APAYAO

Apayao 2nd DEO, Cordillera Administrative Region

2023₱29.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/ NEW ROADS, ABRA- KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL-PINUKPUK), PACKAGE 2, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2024₱28.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/ NEW ROADS, ABRA-KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL-PINUKPUK),PACKAGE 2, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2022₱19.6M
Reported complete (DPWH)
View all 10 projects →

4. Implementation

Contract Amount

₱52,012,766.39

Progress

Past target date (DPWH On-Going)

Start Date

February 26, 2025

Target End

September 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.