Roads23HI0059

CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - CEBU NORTH HAGNAYA WHARF RD - K0015+(-492) - K0015+500, LILOAN, CEBU

CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - CEBU NORTH HAGNAYA WHARF RD - K0015+(-492) - K0015+500, LILOAN, CEBU is a DPWH-tracked public work in Cebu 5th DEO, Region VII. Reported contract value: ₱39,148,000.00. Status: Reported complete (DPWH). Contractor on record: NEW GLOBALDEV CORP. Figures trace to dpwh.

Cebu 5th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cotcot River, Liloan, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu 5th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

9 projects · ₱85.3M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY MABOLO, CEBU CITY

Cebu City DEO, Region VII

2025₱14.6M
Past target date (DPWH On-Going)
No sat.

Construction of Drainage System at Barangay Kalubihan, Cebu City

CEBU CITY (CAPITAL) (CEBU), CEBU, Region VII

2022₱4.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND / OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF ROAD, BARANGAY LOREGA, CEBU CITY

Cebu City DEO, Region VII

2024₱4.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD WITH DRAINAGE, BARANGAY T. PADILLA, CEBU CITY

Cebu City DEO, Region VII

2024₱4.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BANILAD, CEBU CITY

Cebu City DEO, Region VII

2024₱4.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

Construction of Flood Mitigation Structure, Barangay Tejero, Cebu City, Cebu

CEBU CITY (CAPITAL) (CEBU), CEBU, Region VII

2023₱4.9M
Reported complete (DPWH)
View all 9 projects →

4. Implementation

Contract Amount

₱39,148,000.00

Progress

Reported complete (DPWH)

Start Date

April 18, 2023

Target End

March 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.