GAA 2025 DA FMR25IB0129

CONCRETING OF BRGY. 02 POBLACION TO BRGY. SAN ROQUE TO BRGY. BANUYO FMR, BRGY. 02 POBLACION, SAN ROQUE AND BANUYO, MERCEDES, EASTERN SAMAR

CONCRETING OF BRGY. 02 POBLACION TO BRGY. SAN ROQUE TO BRGY. BANUYO FMR, BRGY. 02 POBLACION, SAN ROQUE AND BANUYO, MERCEDES, EASTERN SAMAR is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱4,969,982.94. Status: Past target date (DPWH On-Going). Contractor on record: AICON INDUSTRIES. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Guibuangan, Can-Avid, Eastern Samar
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Eastern Samar DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,969,982.94

Progress

Past target date (DPWH On-Going)

Start Date

August 14, 2025

Target End

September 30, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.