Flood Control and Drainage21FC0043

CONSTRUCTION OF TALISAY RIVER CONTROL STRUCTURE (UPSTREAM SECTION) PHASE 1, BARANGAY CALINTAAN, TALISAY, CAMARINES NORTE

CONSTRUCTION OF TALISAY RIVER CONTROL STRUCTURE (UPSTREAM SECTION) PHASE 1, BARANGAY CALINTAAN, TALISAY, CAMARINES NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱32,337,135.82. Status: Reported complete (DPWH). Contractor on record: BRENTMIN ROOFING ENT. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Talisay Flood Control Structure, Barangay Binauan, Talisay, Camarines Norte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Camarines Norte DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

236 projects · ₱7.6B total · 5 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY MOCONG, BASUD, CAMARINES NORTE, BASUD, C

Region V, Region V

2025₱240.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BASUD RIVER, BARANGAY MAMPILI, BASUD, CAMARINES N

Region V, Region V

2025₱240.1M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY MATOOGTOOG AND BARANGAY

Region V, Region V

2025₱234.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BASUD-LANOT ROAD, MERCED

Region V, Region V

2024₱186.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF MITIGATION STRUCTURE ALONG CULASI RIVER, BARANGAY PAMBUHAN, M

Region V, Region V

2024₱176.9M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG

Region V, Region V

2024₱162.1M
Reported complete (DPWH)
View all 236 projects →

4. Implementation

Contract Amount

₱32,337,135.82

Progress

Reported complete (DPWH)

Start Date

April 5, 2021

Target End

September 26, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.