Flood Control and Drainage24C00486

SUSTAINABLE INFRAS. PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRAS./FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAYABAS RIVER (SEGMENT A), BARANGAY BAYABAS, DONA REMEDIOS TRINIDAD, BULACAN

SUSTAINABLE INFRAS. PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRAS./FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAYABAS RIVER (SEGMENT A), BARANGAY BAYABAS, DONA REMEDIOS TRINIDAD, BULACAN is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱91,669,625.63. Status: Reported complete (DPWH). Contractor on record: M3 KONSTRACT CORP FORMERLY:MARGARITA CONST. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱91,669,625.63

Progress

Reported complete (DPWH)

Start Date

May 20, 2024

Target End

March 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.