GAA 2023 CSSP23FC0052

CONSTRUCTION OF ROAD, BRGY. SUBMAKIN - BRGY. DAGUIT - BRGY. MAOT (PHASE III), LABO, CAMARINES NORTE

CONSTRUCTION OF ROAD, BRGY. SUBMAKIN - BRGY. DAGUIT - BRGY. MAOT (PHASE III), LABO, CAMARINES NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱95,760,790.95. Status: Past target date (DPWH On-Going). Contractor on record: C B GARAY PHILWIDE BUILDERS. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control at Brgy. Tigbinan, Labo, Camarines Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Camarines Norte DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱95,760,790.95

Progress

Past target date (DPWH On-Going)

Start Date

April 5, 2023

Target End

April 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.