Flood Control and Drainage20IE0046

CONSTRUCTION OF PALAPAY FLOOD CONTROL STRUCTURE ALONG PALAPAY RIVER, LEFT BANK SIDE, BRGY. POBLACION, LEYTE, LEYTELEYTE, LEYTE

CONSTRUCTION OF PALAPAY FLOOD CONTROL STRUCTURE ALONG PALAPAY RIVER, LEFT BANK SIDE, BRGY. POBLACION, LEYTE, LEYTELEYTE, LEYTE is a DPWH-tracked public work in Leyte 3rd DEO, Region VIII. Reported contract value: ₱14,253,518.37. Status: Reported complete (DPWH). Contractor on record: GO_SOLID BUILDERS INC. Figures trace to dpwh.

Leyte 3rd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Palapay Flood Control Structure along Palapay River, Left Bank Side, Brgy. Poblacion, Leyte, Leyte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Leyte 3rd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,253,518.37

Progress

Reported complete (DPWH)

Start Date

December 2, 2020

Target End

June 22, 2021

5. Audit