Flood Control and Drainage21HH0163

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - FLOOD CONTROL AND DRAINAGE - DRAINAGE / PROTECTION WORKS - CONSTRUCTION OF DRAINAGE SYSTEM, BARANGAY KASAMBAGAN, CEBU CITY

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - FLOOD CONTROL AND DRAINAGE - DRAINAGE / PROTECTION WORKS - CONSTRUCTION OF DRAINAGE SYSTEM, BARANGAY KASAMBAGAN, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱1,963,667.76. Status: Reported complete (DPWH). Contractor on record: AL SHER CONST. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱25,353,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Barangay Suba, Cebu City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Cebu City DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

13 projects · ₱21.8M total · 0 flags

4. Implementation

Contract Amount

₱1,963,667.76

Progress

Reported complete (DPWH)

Start Date

October 29, 2021

Target End

February 25, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.