Flood Control and Drainage20HH0074

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - FLOOD CONTROL AND DRAINAGE - DRAINAGE / PROTECTION WORKS - CONSTRUCTION OF DRAINAGE SYSTEM, BRGY. DAY-AS, CEBU CITY

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - FLOOD CONTROL AND DRAINAGE - DRAINAGE / PROTECTION WORKS - CONSTRUCTION OF DRAINAGE SYSTEM, BRGY. DAY-AS, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱1,482,999.99. Status: Reported complete (DPWH). Contractor on record: AL SHER CONST. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Brgy. Buhisan, Cebu City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Cebu City DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,482,999.99

Progress

Reported complete (DPWH)

Start Date

March 13, 2020

Target End

June 16, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.