Roads19DN0151

REHABILITATION OF ROADS WITH DRAINAGE SYSTEM (SAN ANTONIO DE PADUA), BRGY. INARAWAN, ANTIPOLO CITY, RIZAL

REHABILITATION OF ROADS WITH DRAINAGE SYSTEM (SAN ANTONIO DE PADUA), BRGY. INARAWAN, ANTIPOLO CITY, RIZAL is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱4,949,858.94. Status: Reported complete (DPWH). Contractor on record: EL-JAKE BUILDERS. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

117 projects · ₱1.9B total · 1 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONST/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMSCONST OF FLOOD CONTROL STRUCTURE ALONG KALERO RIVER, BRGY. SAN RAFAEL, NOVELETA, CAV

Cavite 1st DEO, Region IV-A

2024₱100.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAMCONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONST OF REVETMENT ALONG YLANG-YLANG RIVER, BARANGAY SANTA ISABEL,KAWIT

Cavite 1st DEO, Region IV-A

2024₱95.5M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF MULTI-PURPOSE BUILDING WITHIN ZONE 58 TO 67, MANILA CITY (PHASE III)

North Manila DEO, National Capital Region

2025₱78.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURES, SITIO KAPATAGAN TO BOSO-BOSO RIVER (DOWNSTREAM PHASE 2), K0035+900 ALONG MARIKINA-INFANTA ROAD ANTIPOLO CITY, RIZAL (SECOND DISTRICT)

Rizal 1st DEO, Region IV-A

2020₱55.0M
Reported complete (DPWH)
No sat.

IMPROVEMENT/CONSTRUCTION OF FLOOD CONTROL STRUCTURES, SITIO KAPATAGAN RIVER (UPSTREAM PHASE 7), K0035+900 ALONG MARIKINA-INFANTA ROAD, ANTIPOLO CITY (SECOND DISTRICT)

Rizal 1st DEO, Region IV-A

2019₱55.0M
Reported complete (DPWH)
No sat.

Construction of Flood Control and Slope Protection Structure along Upper Marikina River, Barangay San Jose, Rodriguez, Rizal

MONTALBAN (RIZAL), RIZAL, Region IV-A

2023₱48.2M
Reported complete (DPWH)
View all 117 projects →

4. Implementation

Contract Amount

₱4,949,858.94

Progress

Reported complete (DPWH)

Start Date

July 17, 2019

Target End

November 13, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.