Flood Control and Drainage20DN0011

CONSTRUCTION OF FLOOD CONTROL STRUCTURES, SITIO KAPATAGAN TO BOSO-BOSO RIVER (DOWNSTREAM PHASE 2), K0035+900 ALONG MARIKINA-INFANTA ROAD ANTIPOLO CITY, RIZAL (SECOND DISTRICT)

CONSTRUCTION OF FLOOD CONTROL STRUCTURES, SITIO KAPATAGAN TO BOSO-BOSO RIVER (DOWNSTREAM PHASE 2), K0035+900 ALONG MARIKINA-INFANTA ROAD ANTIPOLO CITY, RIZAL (SECOND DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱55,004,928.78. Status: Reported complete (DPWH). Contractor on record: EL-JAKE BUILDERS. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Sitio Kapatagan River (Upstream), Phase 7, Marikina-Infanta Road, Antipolo City, Rizal
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Rizal 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

117 projects · ₱1.9B total · 1 flags

Other projects by this contractor

View all 117 projects →

4. Implementation

Contract Amount

₱55,004,928.78

Progress

Reported complete (DPWH)

Start Date

December 2, 2020

Target End

July 29, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.