REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, BARORO BRIDGE ALONG MANILA NORTH ROAD

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, BARORO BRIDGE ALONG MANILA NORTH ROAD is a DPWH-tracked public work in La Union 1st DEO, Region I. Reported contract value: ₱4,018,110.74. Status: Reported complete (DPWH). Contractor on record: ARM-ASIA CONST. Figures trace to dpwh.

La Union 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Dike along Amburayan River at Brgy. Porporiket Sudipen, La Union
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0013804

₱130,490.00 · FY2017

Released to Tarangnan National Sa High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

88 projects · ₱749.5M total · 0 flags

4. Implementation

Contract Amount

₱4,018,110.74

Progress

Reported complete (DPWH)

Start Date

March 3, 2017

Target End

April 28, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.