Bridges24IH0098

CONSTRUCTION OF BRIDGE, BARANGAY SAN ROMAN, VICTORIA NORTHERN SAMAR

CONSTRUCTION OF BRIDGE, BARANGAY SAN ROMAN, VICTORIA NORTHERN SAMAR is a DPWH-tracked public work in Northern Samar 1st DEO, Region VIII. Reported contract value: ₱14,428,488.60. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: FOUR JJ CONST. Figures trace to dpwh.

Northern Samar 1st DEO, Region VIII
Region: Region VIII

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱50,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 24IH0098 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2013-05-02 → 2013-05-02

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF BRIDGE, BARANGAY SAN ROMAN, VICTORIA NORTHERN SAMAR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure in the Municipality of San Roque, Northern Samar
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Northern Samar 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

35 projects · ₱320.1M total · 0 flags

4. Implementation

Contract Amount

₱14,428,488.60

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

October 28, 2024

Target End

February 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.