Roads19BG0069

LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - CONCRETING OF ROAD, BRGY. LALOG, LUNA, LSABELA

LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - CONCRETING OF ROAD, BRGY. LALOG, LUNA, LSABELA is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱4,932,387.31. Status: Reported complete (DPWH). Contractor on record: MAR-DEB CONST. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    SARO SARO-ROIVA-19-0009961 · · release to the district office, not itemized per project

    Possible match · score 0.66

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19BG0069 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-02-22 → 2025-06-03

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - CONCRETING OF ROAD,  BRGY. LALOG, LUNA, LSABELA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-19-0009961

₱-37,000,000.00 · FY2019

Released to Rizal 1st District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

229 projects · ₱6.7B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CAUAYAN CITY BYPASS ROAD, ISABELA

Region II, Region II

2024₱149.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R. A. 11239 - PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY - K0349+012 - K0350+700 , K0358+005 - K0358+581

Region II, Region II

2025₱130.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CAUAYAN CITY BYPASS ROAD - PACKAGE 1, ISABELA

Region II, Region II

2023₱115.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF PANANG FLOOD CONTROL STRUCTURE, SECTION 2, SAN AGUSTI

Isabela 4th DEO, Region II

2025₱106.1M
Past target date (DPWH On-Going)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION (COMPLETION) OF CAGAYAN RIVER FLOOD CONTROL PROJECT, BRGY. DISTRICT I, REINA

Isabela 3rd DEO, Region II

2024₱99.0M
Reported complete (100% progress, DPWH status On-Going)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF MAGAT RIVER FLOOD CONTROL PROJECT, BRGY. BANQUERO, REINA MERCEDES, ISABELA

Isabela 3rd DEO, Region II

2024₱99.0M
Reported complete (DPWH)
View all 229 projects →

4. Implementation

Contract Amount

₱4,932,387.31

Progress

Reported complete (DPWH)

Start Date

July 25, 2019

Target End

October 7, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.