Flood Control and Drainage22CI0014

FLOOD MANAGEMENT PROGRAM; CONST/MAINT OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS; CONST OF REINFORCED CONCRETE SLOPE PROTECTION WITH STEEL SHEET PILES FOUNDATION ALONG ABACAN RIVER, BRGY PULUNG MARAGUL, ANGELES CITY, PAMPANGA-STA 1+800-STA 2+550

FLOOD MANAGEMENT PROGRAM; CONST/MAINT OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS; CONST OF REINFORCED CONCRETE SLOPE PROTECTION WITH STEEL SHEET PILES FOUNDATION ALONG ABACAN RIVER, BRGY PULUNG MARAGUL, ANGELES CITY, PAMPANGA-STA 1+800-STA 2+550 is a DPWH-tracked public work in Pampanga 3rd DEO, Region III. Reported contract value: ₱55,632,200.32. Status: Reported complete (DPWH). Contractor on record: B P CRUZ BUILDERS AND TRADING. Figures trace to dpwh.

Pampanga 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structure along Sapang Are Creek, Apalit, Pampanga
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Pampanga 3rd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

35 projects · ₱1.3B total · 0 flags

4. Implementation

Contract Amount

₱55,632,200.32

Progress

Reported complete (DPWH)

Start Date

February 25, 2022

Target End

September 11, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.